Part 9 vs Part 3 Buildings in BC: What Changes for Framing

November 13, 2026 | Category:

6-storey wood-frame multifamily building under construction in the Lower Mainland, BC

Part 9 and Part 3 are two chapters of the BC Building Code, and the question of Part 9 vs Part 3 in BC is settled by the code rather than by the project team. The code looks at how big the building is, how tall it is in storeys, and what it is used for, and that decides which chapter your building is measured against. The two are not a stricter version and a looser version of each other. The difference is who produces the answers and who is on the hook for them. We work on both sides of that line as a commercial framing contractor in the Lower Mainland, and the change we see is rarely in the carpentry. Crossing the line changes the documents, the signatures, and the number of people entitled to look at the work before it gets covered.

Part 9 and Part 3 Are Two Chapters of the BC Building Code, Not Two Building Types

Part 9 reads like a cookbook. It exists so a house, a duplex or a small shop can be built correctly by a competent builder working from requirements the code publishes, without a professional sizing every member. Part 3 is written for buildings big enough, tall enough, or occupied by enough people that the code stops publishing the answers and instead requires qualified professionals to produce them and come back to confirm the building was built the way they drew it.

Everyone on a job site says “Part 9 building” and “Part 3 building” because the consequences are large enough that the chapter name ends up describing the building. The chapter is still a rule book rather than a building type. The real difference is who produces the answer, and who is on the hook for it.

Which Route Your Building Lands On, and Who Decides It

Designer and plan reviewer looking at unrolled building drawings across a municipal office counter in BC

The project does not choose, and neither does the contractor. The code decides, on facts that are settled long before anyone frames anything: the building area, the height in storeys, and what the building is used for. In practice the designer classifies the building and runs the test, and the authority having jurisdiction confirms it when the permit application is reviewed, so a project can rely on the classification from permit review rather than from the first sketch. Where the designer and the authority disagree, there is a formal appeal route, and disagreements of exactly this kind do get decided there.

The Test, and What Building Area Actually Measures

In BC, a building goes onto the Part 3 route once it exceeds 600 square metres of building area, or exceeds 3 storeys, where it is used for homes and apartments, offices and personal services, shops, or medium- and low-hazard industrial work. Either limit on its own is enough, so a project does not have to pass both.

Building area is not the total of your floors. It is the largest horizontal area of the building above grade, measured to the outside of the exterior walls, so a 3-storey building with 250 square metre floors is nowhere near the limit even though its floors add up past it. It is a measurement the designer confirms on the drawings, which means the test gets run off the drawing rather than off a square-footage total.

What the Building Area Leaves Out, and What It Does Not Split

A deck or patio that is not closed in by exterior walls usually sits outside the measurement, and the posts holding it up do not count as exterior walls either. Here is the one that catches projects. A wall between side-by-side homes usually does not split the building for this purpose, so a row of townhouse units is measured as one building unless the walls between them are built as firewalls rather than as fire separations. Which of the two those walls are is something the drawings answer, and it is worth asking early. A row of homes that reads like several small buildings can cross the limit on geometry nobody thought to add up.

Some Uses Are on the Part 3 Route at Any Size

The area and storey test does not reach every building. Buildings used for assembly, for care, treatment or detention, and for high-hazard industrial work are on the Part 3 route whatever their size, and so are post-disaster buildings. A small corner building can be a Part 3 building on its use alone, and that is the half of the test people forget to run. Which route applies follows from what the building is and how it is used, so an addition or a change of use can move the answer. Check it against the current drawings.

Part 9 Still Sets the Legal Requirement, Even If You Design to Part 3

A design team can work to Part 3 criteria on a small building, and one that went to appeal did exactly that, on grounds of complexity and familiarity. What they cannot do is choose which chapter the building is judged against. BC’s building code appeal board has held that a building fitting Part 9 is governed by Part 9, and that Part 9 is what supplies the legal requirement. Designing up is not a safe default, then, because the approach can be refused when the permit application is reviewed.

Crossing the Line Switches On Four Chapters at the Same Time

Ductwork, sprinkler pipe and wiring running above framed walls on a multifamily floor in BC

The rule that puts a building on the Part 3 route does not turn on Part 3 alone. It turns on Part 3, which covers fire protection and occupant safety, Part 4, which covers structural design, Part 5, which covers environmental separation, the building envelope and the assemblies that divide one space from another, and Part 6, which covers heating and ventilation. Four chapters arrive in the same instant.

Fire and Life Safety Gets Bigger, and Finer

Rated assemblies do not start at Part 3. Small buildings already have fire separations, and a rowhouse already separates its units from the rest of the building. What changes on the Part 3 route is the size of the rule set and the fineness of it. Vertical service shafts become their own rated regime, which is part of why shafts and common areas take longer to frame than suites. The detail also gets fine enough to be argued over: whether a small electrical box pushed through a rated ceiling has to be sealed can depend on what that ceiling is doing in the building’s fire plan. The rating and its extent arrive from the drawings.

The Structure Is Designed for Your Building, Not Published

On the small-building route the code publishes prescriptive structural requirements, including the lateral restraint that holds the building against wind and earthquake, and the Province publishes guidance on applying them. On the Part 3 route the structure is designed for your building by a registered professional, and the lateral system arrives as drawings and schedules rather than as rules you look up. The answer stops being in a book the crew can open and starts being in a set with a name on it.

Separations Between Homes Arrive as Drawn Assemblies

On a Part 3 building the separations between homes arrive as drawn assemblies that a professional has signed for, so the assembly on the drawing is the assembly the crew builds, down to the blocking and the backing. Sound gets around a separation as well as through it, which is why continuity where the wall meets the floor, the corridor and the walls running into it is framing work rather than something drywall can fix later. At pricing time the party wall is quoted as the drawn assembly including its continuity, not as a wall with a sheet of drywall on it.

Who Has to Be a Registered Professional, and What They Sign

Engineer stamping and signing a structural drawing sheet at a desk in BC

On the Part 3 route the professionals are not optional, and their involvement is documented on schedules filed at set moments in the job. The documents have names and a sequence, and some small-building projects pick one of them up as well.

The Four Letters of Assurance, and When Each One Is Filed

A coordinating registered professional, an architect or an engineer, is retained by the owner and confirmed on Schedule A at building permit application. A registered professional of record takes responsibility for specific building components and the field reviews that go with them, on a Schedule B filed before construction starts on each of those components. After completion and before an occupancy permit or final inspection, Schedule C-A confirms the coordinating professional met their obligations and Schedule C-B confirms the professional of record met theirs. The coordinating professional makes the disciplines work together. The professional of record owns one area, such as the structure.

Part 9 Jobs That Pick Up a Professional, and the Ones That Do Not

On a small building the trigger is the component, not the building. Letters of assurance are generally not aimed at Part 9 buildings, and they still reach a Part 9 project when it is designed with common egress for its occupants and needs firewalls. They also reach specific pieces of work that fall outside the small-building chapter’s scope, including structural components outside it, ground conditions outside it, and a sprinkler or standpipe system designed to the installation standards the code refers out to rather than to the small-building rules. Outside that case, the code may not require an architect’s design or field review at all, and whatever the local authority asks for beyond that is a municipal matter.

What the Framing Crew Is Handed on Each Route

Carpenters reviewing structural drawings spread over plywood on a framed floor in the Lower Mainland, BC

The craft does not change at the line. The instructions do, and so does the crew’s authority over them. How that work gets sequenced and built is the subject of framing a Type V wood-frame multifamily building. What the two routes hand a crew is a different matter, and it is where most of the surprises sit.

On the Part 9 Route: Requirements You Look Up, and a Permit Set

On the Part 9 route the crew works from permit drawings, the structural requirements the code publishes, and the supplier layouts that come with the trusses or the engineered members. A professional appears for the pieces that sit outside the small-building chapter, and when one does, that piece arrives looking like a Part 3 piece of work on an otherwise Part 9 job. Most residential crews have already met that shape at least once. What matters about that document set is the authority it carries: the answer to a framing question is usually available on site, in the drawings or in the published requirements, so the question gets closed the same day it is asked.

On the Part 3 Route: A Sealed Design With Schedules, and a Name on It

On the Part 3 route the crew works from a sealed structural set produced for this building: member schedules, shear wall schedules, hold-down schedules, nailing schedules and connection details. A named professional stands behind that set, and has committed on a Schedule B to the design and to the field reviews that go with it. The structural choices are not left to the crew’s judgment, because the design was produced for this building rather than looked up.

The set is also one of several. The structure comes from one professional of record, and the architectural and mechanical work comes from others, coordinated above them. So a framing question can have more than one owner, and finding the right owner is part of the job.

Substitution Stops Being a Field Decision

This is the single most common culture shock when a residential crew steps onto its first Part 3 job. On a small building a crew can often swap a member for an equal or better one within the requirements the code publishes. On a Part 3 building the member came out of a professional’s model for this building, so changing it is a question back to the designer rather than a call on site.

The practical half of that is what nobody tells a first-time Part 3 crew. The cost of a substitution is no longer material, it is a day of someone’s time and a paper trail. The crews that handle it well read the schedules before the first run and ask early, while an answer is still cheap.

What the Crew Can Still Settle on Site

The means and methods stay with the crew. How the work is staged, which walls go up in what order, and how material is landed and moved are still theirs to decide and theirs to own. So is how the crew organizes itself across a repetitive floor, and so is holding the dimensions the drawings call for. None of it is a smaller job on a Part 3 building, and a repetitive building rewards a crew that can plan a floor and then repeat it cleanly.

What moves is anything that changes what the building is made of or how it is connected. That line is clear enough on site once a crew has it. If the question is about sequence, answer it. If the question is about the design, send it.

Who Is Entitled to Look at the Work Before It Is Covered

Engineer in a hard hat checking a framed corridor with the walls still open on a BC multifamily building

Municipal inspections happen either way, and the framing rough-in inspection works the same way on both routes. The Part 3 route adds a second set of eyes with its own obligation, and that addition is what reshapes a framing schedule.

Field Review Is the Designer’s Own Look, Not the City’s

Field review is the engineer’s or the architect’s own look at the work on site, at the points they judge necessary, to confirm it was built the way they drew it. It is periodic, and it is a separate obligation from the municipal inspection, which means a crew on a Part 3 job is not being checked once.

On a Part 3 building a wall is closed when everyone entitled to look at it has looked at it, not when the framing is done, so sheeting ahead of that creates rework. A Part 3 framing program has to be planned around other people’s site visits, and the first run through a repetitive floor matters most, because a detail wrong in the first unit is wrong in all of them.

The Final Schedules Stand Between the Finished Building and Occupancy

The professional’s field review is a gate rather than a courtesy. The building does not get occupied until the final schedules confirm the reviews were done, so a review that was skipped surfaces at the end of the job, when the consequence is a delayed occupancy rather than an hour’s rework. On the small-building side the picture is simpler. Where the code does not require an architect’s professional design, it does not require their field review records or their final schedule either, so a Part 9 job can finish on the municipal inspection alone.

Part 9 vs Part 3 Side by Side in BC

The obligations do not arrive one at a time. They arrive together, with the classification, so a project that crosses on area alone picks up the same document load, the same professionals and the same review sequence as one that crosses on storeys. A developer who trimmed a building to sit just under one limit and crossed the other has not reduced anything.

What changesPart 9 routePart 3 route
Which buildings land hereHousing and small buildings: houses, duplexes, rowhouses and small commercial buildings, until the project meets one of the Part 3 triggersA building goes onto this route once it exceeds 600 square metres of building area, or exceeds 3 storeys, where it is used for homes and apartments, offices and personal services, shops, or medium- and low-hazard industrial work. Buildings used for assembly, for care, treatment or detention, or for high-hazard industrial work are on this route at any size, and so are post-disaster buildings
Who produces the structural designThe code publishes prescriptive requirements, with a professional brought in for components outside the small-building chapter’s scopeA registered professional designs the structure for this building
What the framing crew is handedPermit drawings, the structural requirements the code publishes, and supplier layoutsA sealed structural set with member, shear wall, hold-down and nailing schedules and connection details
What gets filed, and whenGenerally no letters of assurance, unless the project has common egress and needs firewalls, or a component falls outside the small-building chapterSchedule A at permit application, Schedule B before each component starts, Schedule C-A and Schedule C-B after completion and before occupancy
Who looks at the workMunicipal inspectionsMunicipal inspections, plus the professional’s own field reviews, with the final schedules standing between the finished building and occupancy
Changing a member in the fieldOften available to the crew within the requirements the code publishesA question back to the designer

What the Line Does Not Decide

Wood stud framing built against a grey concrete wall on a Lower Mainland construction site

Some things get read into this line that are not in it, and they cost money when they are assumed rather than checked.

A Part 3 Building Is Not Automatically Concrete or Steel

Six storeys of combustible wood frame is a Part 3 building, and most of the Lower Mainland’s mid-rise stock is exactly that. Permission to build a Part 3 building in wood arrives as a package of conditions, and past the limits of that package the building goes to noncombustible construction. Extra requirements for tall buildings also begin at a defined height above grade, so how grade works out on a sloped site can change which rules apply. The storey and height ceilings themselves are the subject of how many storeys a wood-frame building can be in BC.

Energy Requirements Are Set Separately, on Their Own Scale

A small building can be pushed onto the national energy code when the combined total floor area of its non-residential occupancies exceeds 300 square metres, or when it contains a medium-hazard industrial occupancy, so a mixed-use project can land there without crossing the Part 3 line at all. That threshold is a different measurement again, adding up the floor area of the non-residential parts storey by storey rather than taking one horizontal slice. The two routes also carry their own sets of steps, each with its own base, so a step on a small building does not compare to a step on a large one. Your municipality confirms which step applies.

Where Crossing the Line Actually Costs a Project

The framing itself does not change much at the line, which is why a Part 3 job priced off small-building production rates is priced wrong. The craft is the same. The verification load around it is not, and that load is what the price has to carry. The decision that is expensive to reverse sits further back: designing a building to land just short of the limits without first confirming the uses and the building area. A late reclassification lands on the structural design, the permit set and the professional appointments at once.

Framing Part 3 Buildings Across the Lower Mainland

A crew that works on both sides of the line is useful to a project that has just crossed it: the habits a Part 3 job requires are the ones a residential crew otherwise learns under pressure. We are an ITA-approved Red Seal Carpentry training authority, and Red Seal carpenters lead our work in the field, which makes a crew reliable against a document set that does not bend. Our work runs across complex custom homes and commercial multifamily, so our crews have built on both routes. They are stable crews with low turnover, which is what makes the first run through a repetitive floor hold for every floor after it. Anvil West is owner-led by Luke Creighton, Vancouver-based and in business since 2013.

We price and build commercial wood framing on the far side of this line, and the best time to bring us in is while the structure and the price are still open. If your project is anywhere near it, get in touch and walk us through the site, the uses, the building area and the storey count.

Frequently Asked Questions

What Is the Difference Between a Part 9 and a Part 3 Building in BC?

Part 9 and Part 3 are two chapters of the BC Building Code, not two kinds of building, and the code decides which chapter your building is measured against. The decision runs on the building area, the height in storeys and what the building is used for. The practical difference is who produces the answers: on the small-building route the code publishes them, and on the Part 3 route registered professionals produce them for your building and then confirm it was built the way they drew it.

Is a 4-Storey Apartment Building a Part 3 Building?

Yes. A building goes onto the Part 3 route once it exceeds 3 storeys, or once it exceeds 600 square metres of building area, where it is used for homes and apartments, offices and personal services, shops, or medium- and low-hazard industrial work. Either limit does it on its own, so a 4-storey apartment building is on the Part 3 route on its height whatever its area. Building area is the largest horizontal area of the building above grade rather than the total of the floors.

Can You Design a Small Building to Part 3 Instead of Part 9?

You can design a small building to Part 3 criteria, and some teams do, on grounds of complexity or familiarity. What you cannot do is choose which chapter your building is judged against, and that is the part that catches design teams. A building that fits the small-building chapter is governed by it, so designing up is not a safe default and the approach can be refused when the permit application is reviewed.

Does a Part 9 Building Need an Engineer?

Sometimes, and the trigger is the component rather than the building. A Part 9 project picks up a registered professional for a structural component outside the small-building chapter’s scope, for ground conditions outside it, for a sprinkler or standpipe system designed to the installation standards the code refers out to, or where the building is designed with common egress for its occupants and needs firewalls. Outside cases like those, the code may not require an architect’s design or field review at all.

Does Building Area Mean All My Floors Added Together?

No, and this is the question that decides which side of the line some projects land on. Building area is the largest horizontal area of the building above grade, measured to the outside of the exterior walls, so floors adding up past the limit says nothing on its own. Walls between side-by-side homes usually do not split the building for this measurement either, so a row of units can be measured as one building.

Does a Part 3 Building Have to Be Concrete?

No. Six storeys of combustible wood frame is a Part 3 building, and most of the Lower Mainland’s mid-rise stock is built that way. The permission to build a Part 3 building in wood arrives as a package of conditions attached to the building’s size, use and protection, and past the limits of that package the construction goes noncombustible. Concrete and steel show up on larger and taller buildings because of what the package stops covering, not because the Part 3 chapter asks for them.

Does the Framing Crew Work Differently on a Part 3 Job?

Same craft, different authority. The crew builds to a named professional’s design rather than to requirements it can look up, a substitution goes back to the designer instead of being settled on site, and a wall is closed once everyone entitled to look at it has. Sequence, staging and dimensional control stay with the crew, and on a repetitive building they matter more rather than less. What a crew gives up is the right to change what the building is made of or how it is connected.

Recent Posts

Part 9 vs Part 3 Buildings in BC: What Changes for Framing

How Many Storeys Can a Wood-Frame Building Be in BC?

What Lumber Is Used to Frame Houses in BC? Framing Lumber Grades and SPF Explained

Quality Control for Offsite Framing: What to Verify and When

Open vs Insulated Wall Panels: Choosing for Your Build

Speak With
Our Team